国内英语新闻:China's cranes to promote Namibia's port construction
WINDHOEK, Feb. 9 (Xinhua) -- Namibia's port in the coastal town of Walvis Bay will become the "most brilliant pearl on the Atlantic Coast of southwest Africa" with the delivery of four ship-to-shore (STS) cranes manufactured by China, the Chinese ambassador to the country said Friday.
Chinese Ambassador to Namibia Zhang Yiming made this remark at a ceremony held at the harbor town, about 400 km from the capital Windhoek.
The cranes, manufactured by China's Zhenhua Port Machinery Company, will be deployed at the new container terminal that is expected to be completed by mid-2019.
The project, developed by the state-run China Harbor Engineering Company (CHEC) since 2014, will have a throughput capacity of 750,000twenty-foot equivalent units (TEUs) per year.
Expected to be completed by mid-2019, the terminal will have two 600-meter-long berths and accommodate container vessels of 8,000 TEUs.
Zhang said the arrival of the cranes is not only key to the port's construction, but also indicates that the project is about to be completed soon, making Walvis Bay the most splendid city on the Atlantic Coast of southwest Africa.
"It can be said that this is the benchmark project for China-Namibia friendly and pragmatic cooperation, which symbolizes the great attention of our leaders to our relations and the brotherhood between our people," Zhang said.
Chief Executive Officer of Namibia Ports Company (Namport) Bisey Uirab said the ship-to-shore cranes are major components of the new container terminal project and their application is regarded as a milestone in the life cycle of the port as it is the very first time that this type of cranes is being deployed.
"The ship-to-shore crane is the largest container-handling equipment and will improve efficiencies and enable faster ship turnaround time, which will make our terminal attractive for shipping lines," Uirab said.
He also said the STS cranes can load or offload up to 40 containers per hour while a mobile harbor crane can only deal with 15 containers per hour on average.
Uirab said the cranes, each of which cost 110 million Namibian dollars (about 9 million U.S. dollars), can attain a height of up to 70 meters during operation.
If the booms are raised, Uirab added, the crane's height can reach 122meters, while the boom reaching from the seaside leg will be 69 meters long.
"The cranes run on two crane rails which are 100 feet (about 30.5 meters) apart, and they run for the full 600-meter length of the quay wall," he said.
Earlier this month, Namport said the Namibian 344 million-U.S.-dollar container terminal currently under construction in Walvis Bay is 76 percent completed.
The new port will also be connected to the existing port's road and rail networks as well as communication systems.
相关文章
- 英语文摘:China urges G7 to cease interfering in its internal affairs
- 英语文摘:HKSAR gov't strongly refutes G7, EU statements on chief executive election
- 英语文摘:Xi's keynote speech at opening ceremony of Boao Forum for Asia Annual Conference 2022 publ
- 英语文摘:Xi attends ceremony marking centenary of Communist Youth League of China
- 英语文摘:Xi talks with Macron over phone
- 英语文摘:External interference in Hong Kong affairs doomed to be self-defeating: Commissioner's off
- 英语文摘:Chinese spokesperson slams Western countries smearing Hong Kong election
- 英语文摘:China calls for equal, balanced global development partnership
- 英语文摘:Xinhua Headlines: A look at younger generation on China's new journey
- 英语文摘:Chinese vice premier reiterates dynamic zero-COVID policy